Oil and Gas Archives - CEG Construction Engineering Group Experts in construction solutions and applications Mon, 04 Apr 2022 11:10:19 +0000 en-US hourly 1 https://wordpress.org/?v=6.8.3 203067828 Rumaila Oil Field | Evaporation Pond Lining https://ceg.zcreations.com/portfolio-items/rumaila-oil-field-evaporation-pond-lining/ Mon, 07 Dec 2015 00:55:52 +0000 https://ceg.zcreations.com/?post_type=avada_portfolio&p=1771 CEG supplied and installed HDPE geomembrane lining of 2mm thickness for evaporation ponds at Rumaila Oilfield.

The post Rumaila Oil Field | Evaporation Pond Lining appeared first on CEG Construction Engineering Group.

]]>

Oil and Gas

CEG supplied and installed HDPE geomembrane lining of 2mm thickness for evaporation ponds at Rumaila Oilfield.

Supplier: Geoplas

Project Details

DATE

2025

CLIENT

China National Petroleum Company

PROJECT TYPE
AREA (m2)

18000

The post Rumaila Oil Field | Evaporation Pond Lining appeared first on CEG Construction Engineering Group.

]]>
1771
Lukoil WQ2 Oilfield | Central Processing Facility https://ceg.zcreations.com/portfolio-items/lukoil-wq2-oilfield-central-processing-facility/ Sat, 07 Dec 2013 00:55:52 +0000 https://ceg.zcreations.com/portfolio-items/rumaila-oil-field-evaporation-pond-lining-2/ Central Processing Facility – CPF and Well Clusters at WQ2 major rehabilitation of concrete work, industrial coating, and HDPE lining, insulation and fireproofing coating

The post Lukoil WQ2 Oilfield | Central Processing Facility appeared first on CEG Construction Engineering Group.

]]>

Oil and Gas

The Project is to build Central Processing Facility (CPF) by Samsung Engineering to LUKOIL Co. at West Qurna II (WQ2), and three Well Clusters.

CEG, started the first concrete repair contract with the main Concrete supplier to the project (77 Insaat), CEG executed the work which included but not limited Repair concrete cracks, Expansion joints, supply of concrete admixtures for the new foundations of the project, Cement Grout and Epoxy Grout for the most of the foundations in the project.

CEG, executed the same repairs for another three well clusters.

BASF Chemicals material were mainly used.

And with the progress of work on site and with a good performance, CEG executed the following work:

  • 12000m2 of HDPE for Evaporation Ponds, thickness 2mm.
  • Insulation of piping work at the CPF of 1800m of different diameters, Armacell materials were used
  • Fireproofing coating – CEG applied Cementitious fireproofing for the most steel structure at the site
  • Applying of Industrial Epoxy flooring for the Warehouses of an area of 40000m2
  • Applying Ceramic Coating for the flare area using Belzona Materials
  • Tar Epoxy coating for the foundation area of the Ground Power transformers
  • Applying of Ant-Corrosive and protective coating for the oil storage tanks and water tanks

Project Details

DATE

2025

CLIENT

Lukoil, WQ2 Oilfield

PROJECT TYPE
AREA (m2)

12000 + 40000

The post Lukoil WQ2 Oilfield | Central Processing Facility appeared first on CEG Construction Engineering Group.

]]>
1982