Commercial Archives - CEG Construction Engineering Group Experts in construction solutions and applications Sun, 27 Mar 2022 15:45:42 +0000 en-US hourly 1 https://wordpress.org/?v=6.8.3 203067828 Baghdad Pepsi Factory https://ceg.zcreations.com/portfolio-items/baghdad-pepsi-factory/ Wed, 07 Dec 2016 00:55:52 +0000 https://ceg.zcreations.com/?post_type=avada_portfolio&p=1810 Industrial flooring of 8000 m2 using 2mm thickness epoxy materials for Baghdad Pepsi Factory.

The post Baghdad Pepsi Factory appeared first on CEG Construction Engineering Group.

]]>

Commercial

The client planned to increase the production lines for their factory which required removing old flooring for the existing production line.  CEG, executed the work that include removing for the old flooring system, applying a self-leveling flooring, expansion joints and industrial epoxy flooring.

For the new production lines CEG executed Epoxy grout for the new machinery and expansion joints with surface preparation and industrial Epoxy flooring.

Material supplier; Fosroc Chemicals

Project Details

DATE

2025

CLIENT

Baghdad Pepsi Factory

PROJECT TYPE
Area (m2)

8000

TAGS | SKILLS

The post Baghdad Pepsi Factory appeared first on CEG Construction Engineering Group.

]]>
1810
KIA Motors Showroom https://ceg.zcreations.com/portfolio-items/kia-motors-showroom/ Sun, 07 Dec 2014 00:55:52 +0000 https://ceg.zcreations.com/?avada_portfolio=maine-modernity-2 KIA Motors opened a showroom and a maintenance center.  CEG did the surface preparation fix the damaged areas with mortars and bonding agents a self-leveling and an industrial epoxy coating of 2.5 mm thickness for an area of approximately 5000 m2.

The post KIA Motors Showroom appeared first on CEG Construction Engineering Group.

]]>

Commercial

KIA Motors opened a showroom and a maintenance center.  CEG did the surface preparation fix the damaged areas with mortars and bonding agents a self-leveling and an industrial epoxy coating of 2.5 mm thickness for an area of approximately 5000 m2.

Project Details

DATE

2025

CLIENT

KIA Motors

PROJECT TYPE
AREA (m2)

5000

TAGS / SKILLS

The post KIA Motors Showroom appeared first on CEG Construction Engineering Group.

]]>
1725
Iraqi Red Crescent & Alwaziria Hospitals https://ceg.zcreations.com/portfolio-items/iraqi-red-crescent-alwaziria-hospitals/ Sun, 07 Dec 2014 00:55:52 +0000 https://ceg.zcreations.com/portfolio-items/maine-modernity-2-2/ Epoxy system Anti-static flooring for 4 operating theaters, of an area of 1500 m2 thickness 3mm.

The post Iraqi Red Crescent & Alwaziria Hospitals appeared first on CEG Construction Engineering Group.

]]>

Commercial

Iraqi Red Crescent Hospital and Alwaziria Hospital are some of the few hospitals specialized in maternity in Baghdad.  This project was commissioned due to the increase in demand for adding wards and operating theaters, as well as the need of developing the existing operating theaters.

CEG, was contracted to remove the old flooring tiles repair the surface clean the joints and repair the edges.

CEG, applied Anti-static epoxy flooring for the operating theater and anti-fungus and Bacterial walls and the rest of the hospitals Corridors, and all other facilities.

Material used: BASF Chemicals

Project Details

DATE

2025

CLIENT

Iraqi Red Crescent & Alwaziria Hospitals

PROJECT TYPE
AREA (m2)

1500

TAGS / SKILLS

The post Iraqi Red Crescent & Alwaziria Hospitals appeared first on CEG Construction Engineering Group.

]]>